Name: Rehabilitation Hospital Peoria
Contract Amount: $$547,930.00
Owner: America Development
General Contractor: Adolfson & Peterson Construction
Year: 2023
Earthwork and Site utilities for a new 3-story, 49,000 gross sf facility developed as a self-contained and independently licensed Inpatient Rehabilitation Hospital. EARTHWORK Scarify and compact - 8,182 SY Excavation to fill - 3,638 CY Pad / foundation over-excavation - 2,414 CY Finegrade pad - 1,683 SY Non-expansive soil backfill under slab - 374 CY Asphalt roadway abc placement - 1,302 Tn Concrete roadway abc placement - 237 Tn Curb - cut and backfill - 3,073 LF Rip-rap placement - 35 SY Grading - parkway/landscaping - 7,613 SY Grading - sidewalk - 1,529 SY Grading - concrete on 4” abc - 1,065 SY Grading - roadway - 5,858 SY 3” Ac paving - heavy duty - 3,286 SY 2” Ac paving - light duty - 2,572 SY Parking lot striping and signage - 1 LS Haul off spoils - 1,152 CY Sewer Line: 6” PVC - 177 LF Fire Line: 6” C900 - 130 LF 8” C900 - 375 LF 6” DIP - 96 LF Water Line: 3” PVC - 128 LF 2” Hard Copper - 7 LF