Name:
Rehabilitation Hospital Peoria
Contract Amount:
$$547,930.00
Owner:
America Development
General Contractor:
Adolfson & Peterson Construction
Year:
2023
Earthwork and Site utilities for a new 3-story, 49,000 gross sf facility developed as a self-contained and independently licensed Inpatient Rehabilitation Hospital.
EARTHWORK
Scarify and compact - 8,182 SY
Excavation to fill - 3,638 CY
Pad / foundation over-excavation -
2,414 CY
Finegrade pad - 1,683 SY
Non-expansive soil backfill under slab -
374 CY
Asphalt roadway abc placement -
1,302 Tn
Concrete roadway abc placement -
237 Tn
Curb - cut and backfill - 3,073 LF
Rip-rap placement - 35 SY
Grading - parkway/landscaping -
7,613 SY
Grading - sidewalk - 1,529 SY
Grading - concrete on 4” abc -
1,065 SY
Grading - roadway - 5,858 SY
3” Ac paving - heavy duty - 3,286 SY
2” Ac paving - light duty - 2,572 SY
Parking lot striping and signage - 1 LS
Haul off spoils - 1,152 CY
Sewer Line:
6” PVC - 177 LF
Fire Line:
6” C900 - 130 LF
8” C900 - 375 LF
6” DIP - 96 LF
Water Line:
3” PVC - 128 LF
2” Hard Copper - 7 LF