Contract Amount: $5,031,605.72
Owner: Gila River Indian Community
General Contractor: REDPOINT Contracting
Year: 2017
Construction of a new water main (approximately 23.5 miles) to replace an existing undersized and/or failing pipeline in the Casa Blanca Area. Work also included all required fittings, air release valve assemblies, 91 Fire Hydrants Complete w/ Tee, 6-inch C900, 6” valve box, plugs and appurtenances, 130 concrete encasements at sewer crossings, testing and approvals, trenching, backfilling, compaction and testing, site clean-up, and demobilization.